postheadericon Big Boulder looking awesome!
















The big twisted and curved panels were fitted to the Big Boulder last weekend and finally we can see what an impressive shape we've created. The Big Boulder has potential for all grades of problem as well as some route length link ups - we can't wait to climb on it! Meanwhile structural steels & timbers are going up around the pit and it won't be long before this starts getting panelled.








Wednesday, 9 June 2010

postheadericon The Modular Wall takes shape




The Beacon have a unique modular system which has been configured to give some great features including chimneys, aretes, corners & an abseil platform. A perfect area for group use.
Sunday, 6 June 2010

postheadericon Big Rock's getting bigger!







We're sorry we haven't updated recently, but things have been happening, as you can see. The pit is now finally formed, and will be left for a little while for the concrete to cure and dry. In the meantime, bouldering walls have been put up all along one side of the unit, including all angles from slightly slabby to worryingly overhanging. Next to that the big, freestanding boulder is also taking shape. The preformed modular wall is quickly going up across the other side of the chasm in the group area. Watch this space to see more bouldering and group areas sprouting up either side of the pit soon.
Saturday, 8 May 2010

postheadericon Bouldering Wall Construction Starts
















Climbers from the Beacon arrived on site at the beginning of the week to start construction of the climbing walls. They'll be here for about two months. The 'north wall' of the bouldering area has been set out, and will shortly be ready to receive the climbing panels that have already been fabricated (in the Beacon's North Wales factory).










In the meantime, the pit is progressing well. The reinforcement arrived during the week, and concrete pouring for the retaining walls and floor will start on Monday.
Wednesday, 21 April 2010

postheadericon Perfect Pit Preparation








The Pit is dug! 39 lorry loads later we have a Pit, and it looks enormous. Next up - the concrete floor, retaining slabs and the stairs.


The windows overlooking the Centre from the upstairs viewing gallery are in as well.
Thursday, 15 April 2010

postheadericon Pit Progress







Progress has been good in the Unit these last few days. The concrete floor has been broken up and the serious digging of the Pit has started. Meanwhile, Pete the Builder is rushing to get as much done as possible before he heads off to Nepal in a couple of weeks. The electrics and plumbing are well underway, as are the changing rooms, the office and the cafe kitchen.
Wednesday, 14 April 2010

postheadericon Meanwhile in the Beacon workshop...


Just to prove it isn't all about just ripping things apart at this stage here is a photo of a section of new climbing wall currently being put together in the workshop. The 'Wave' is a style of bouldering wall unique to the Beacon and this is the biggest we've built so far. The Wave along with a truly enormous boulder will form the centrepieces of the main bouldering area.